THE MAXWELL CONSTRUCTION UPDATE APRIL 2018

 During the month of April, the project saw the Plant Deck completed; all scaffold dropped, final screens installed and painting complete to all elevations

Internal finishes saw the paint, joinery and tiling complete. External Services works are now 100% complete including utility crossover; and landscaping commencing. May will see the development moving closer to practical completion with QFES inspection top be completed and certification and defecting commencing