MAGNUS CONSTRUCTION UPDATE AUGUST 2017

July was a busy month with an additional three levels constructed including level 10. This leaves one more concrete slab to be constructed early this month.
Read more

FABRIC CONSTRUCTION UPDATE JULY 2017

Hutchinson Builders have commenced the Operational Works construction requirements for the Brisbane City Council.
Read more

MAXWELL CONSTRUCTION UPDATE JULY 2017

Excavators continue to work away in tough conditions at Maxwell. Recent rain events has not stopped works progressing and the bulk of the basement has now been excavated.
Read more

MAGNUS CONSTRUCTION UPDATE JULY 2017

June was a big month for the site with the completion of the Level 7 slab and commencement of the internal works on Ground, Level 1 and Level 2.
Read more

MAGNUS CONSTRUCTION UPDATE JUNE 2017

May has been a busy month at Magnus. Significant structural progress has been made with the completion of Levels 2 and 3 concrete slabs and Level 4 due for completion later this week.
Read more

MAXWELL CONSTRUCTION UPDATE JUNE 2017

The month of May has seen solid progress onsite. Whilst it may not look significant from the casual observer’s perspective, the continued excavation in tough conditions has continued on programme.
Read more

FABRIC CONSTRUCTION UPDATE JUNE 2017

Following Hutchinson’s commencement onsite, demolition works have now been completed in readiness for the imminent commencement of earthworks.
Read more

Maxwell Construction Update May 2017

Construction is continuing as planned at Maxwell Street with the basement excavation progressing well and the construction and installation of the basement walls and rock anchors commencing. The ground conditions have remained as expected and solid progress is continuing. Taking this into consideration, the team maintain that a 14-Month constructio
Read more

BLOOM CONSTRUCTION UPDATE MAY 2017

Stage 5B Civil Works are fully complete with housing construction well underway. Stage 7A and 7B construction is well progressed with earthworks completed across these stages.
Read more

FABRIC CONSTRUCTION UPDATE MAY 2017

Hutchinson’s have now commenced work on-site, with the demolition of the internals of the existing buildings.
Read more

About

PointCorp Development

We’re building tomorrow’s premium properties, bringing together the finest design and construction talents to realise the true potential of our exceptional locations.
Read more