The Maxwell is on the way up. The basement excavation is now complete and basement 2 slab is complete. The basement 1 suspended slab is in two pours the first of which has been completed. By mid September the ground floor should be complete. Design has been finalised and all significant trades have been appointed. The project is progressing well and is forecast for completion 1st quarter 2018.
For further information, contact Jeanette Jensen on 0400 064 774 or email jeanette@ypmgroup.com.au. Alternatively, register your interest on The Maxwell Website.