THE MAXWELL CONSTRUCTION UPDATE FEBRUARY 2018

During the month of February, The Maxwell project achieved a number of construction milestones with the following key areas of works completed. Pointcorp saw the completion of the Pool structure and the dropping of the upper level scaffold. This removal of scaffold unveiled the first level of window privacy screening and external painting.

Internally saw ceiling and partitions completed to level 3 and the framing completed on level 4. On the lower levels the first coat of painting has been completed and joinery installation commenced.

Despite January being a short month after Christmas fair weather over the course of the month meant programme targets were meant with the practical completion date being maintained.