Construction Updates

Maxwell Construction Update April 2017

A stone’s throw from the city, New Farm remains one of Brisbane’s most desirable addresses. A blend of culture, arts and cuisine, it’s home to a vibrant lifestyle with a distinctly euro flavour. On the city side of this eclectic village, with postcard views to the city, river and Kangaroo Point, the Maxwell is currently under construction, and soon to be perfectly positioned for cosmopolitan living in unmistakable style.

Work has commenced onsite at Maxwell Street. We currently have excavators onsite remove soil and rock from the site to create both basement 1 and 2. The ground conditions have proved to be as expected and solid progress is being made. The team believe the 14 month construction programme is achievable and we expect completion in May 2018.

 

For further information, contact us on 0400 064 774, or register your interest on the Maxwell Website