We are very pleased to announce the structure for Magnus is now complete. The final level has been poured and the last of the precast installed. This is a significant milestone for the project and owners will be exceptionally happy with the view offered from the roof deck pool and amenities. Attention now turns to the apartment finishes.
These are progressing well with wall framing completed to Level 6 and the first kitchens installed on Level2. Bathroom tilting and internal painting has also commenced. Completion is still on target for 1st Quarter 2018.
For further information, contact us on: 0400 064 774 or register here on the Magnus Website.