In the month of September, the structure continued to progress well with the Level 3 slab begun pouring on Friday the 28th of September.
The precast concrete panels were erected along the boundary wall and are now standing at Level 5. Formwork has been stripped on the lower levels allowing internal works to commence on the Ground Floor. We are continuing to strip the formwork on Level 1, which once complete will see the commencement of internal works on the apartments.
Fabric construction will continue to progress significantly with both structure trades and internal trades now expected to work concurrently.