Prior to Christmas the builder completed all structural concrete pours with the lift shaft lid topping the building out on Friday 21st December as per their target program.
Work on site recommenced after the Christmas break on Monday 7th January and with no rain to speak of they are continuing as per program. Within the next month the scaffold will start to slowly drop with external façade finishes being applied. All levels internally are progressing with work across the 7 apartment levels taking place.
Finishes to the pool level are also commencing in the near future (including the pool) with structural blockwork now complete.