FABRIC CONSTRUCTION UPDATE APRIL 2018

Although we have been challenged by mother nature, April has brought excavation the base of the car stackers is complete. Fine weather permitting, bulking out of the site will continue over the next couple weeks or so with detailed excavation following.

The first basement slab is targeted to be poured by mid-June which is two weeks behind the original target date. With the Crane base now in and the erection of crane occurring soon, we will see an acceleration in works to get back on program.