The construction at Bloom Coomera has progressed throughout October to a point where the civil and electrical construction will be complete within the next fortnight for Stage 5A, 6A and 6B which will allow title registration of these lots in Mid-November.
The construction that has occurred over the last month has included the completion of roads, the finalisation of lots and the completion of the installation of the electrical, communication and gas services. The landscape construction which includes the installation of street trees and laying of turf as well as the landscaping of the parks is due to commence on the 12/11.
The Build Team have continued progressing with the construction of the Stage 8A and 8B houses with a large number being completed and handed over to happy new owners. Please see our Flyover Video below to see the current status of Bloom Coomera.